I-70 Thru Glenwood Canyon Fully Open

April 13, 2016

Interstate 70 through Glenwood Canyon is fully open nearly two months after rockfall caused major damage.  

In mid-February, I-70 closed for nearly a week. Then it reopened to head-to-head traffic followed by single-lane openings in each direction.  

Credit Tracy Trulove / CDOT
Rockfall on I-70 thru Glenwood Canyon.

Tracy Trulove, with the Colorado Department of Transportation, says urgent repairs to the road are now completeall four lanes are accessible.

"Originally, when the emergency project was planned, we were talking about May 5 being our opening so this was great to have it open 23 days ahead of schedule," she says.

Trulove says CDOT is still in the design phase for further rockfall mitigation for the canyon. Those repairs could cause future closures.

Copyright 2016 KVNF-FM. To see more, visit KVNF-FM.

You care!

You are one of the KRCC readers who wants to know what is really going on in Southern Colorado these days. We have got just the thing for people like you: the KRCC Weekly Digest. Sign up here and we will see you in your email inbox soon!